|
After a £40 million major upgrade by Metronet Rail, delivering
faster journey times, a more reliable service and, ultimately, more
passenger capacity.
The entire railway environment on the 108-year-old line, from journey
times to station facilities, has been greatly enhanced for passengers.
Specifically this provides:
* quicker journey times
* A smoother ride
* Smarter, more secure trains all 20 carriages were lifted
out and transported 170 miles to Doncaster for refurbishment including
the installation of a CCTV system
* Smarter station platforms redecorated with new livery, badges
and decals
* More reliable trains a separate power supply to the depot
will enable 24-hour maintenance
Journey times are now at least 30 seconds faster on the round trip.
From November, this will be used to introduce another two trains per
hour, improving capacity by 2,000 passengers per hour.
A new service control system, to be commissioned early next year,
will allow five trains to operate instead of four, further improving
the timetable and delivering in total 20-25% more rush hour trains.
Stephen Hall, Chief Programmes Officer for Metronet, said: Passengers
today clearly appreciated the quality of what we have delivered. The
station platforms are significantly better and the trains are vastly
improved. The ride before was jolting and is now smooth and journeys
are more reliable. Speed restrictions have been removed and from early
next year rush-hour capacity will be increased by up to 25 per cent.
The upgrade has been a complex project, completed within a challenging
timescale. The task was made harder by the fact the line is physically
isolated from the rest of the Underground most materials and
equipment could only be lifted in and out of the underground depot.
In total, there were 14,000 separate crane lifts.
Track
Metronet and its principal contractor Balfour Beatty Rail has renewed
all the tunnelled track between the two stations, replacing wooden
sleepers with concrete and old rail with new. A huge amount of work
has gone into its design to ensure the best ride possible within the
constraints of the 108-year-old tunnels. Coupled with the concrete
sleepers is a new track drainage system, which together will reduce
signal failures from the water that seeps in.
Signalling
Metronet has also renewed the signal equipment rooms, modified trackside
signalling equipment and is installing a new service control system
which will allow all five trains to operate instead of four. This
is expected to deliver a 20-25 per cent improvement in capacity when
the system is commissioned, early next year.
Trains
The trains have been painted in the Underground's distinctive red,
white and blue livery and seats reupholstered and sagging frames and
springs replaced. Grab rails and grab poles have been recoated in
the light turquoise colour of the line and scratched and scored windows
replaced and anti-graffiti film applied. CCTV cameras have been fitted
throughout.
Station platforms
Floors have been skimmed and polished, seats have been redecorated
and the tiling repaired. There are new signs, freshly painted walls
and ceilings and at Bank display boards to end the frustration
of not knowing from which platform the next train will depart.
As part of the job, engineers disposed of:
3,806 tonnes spoil
2,515 timber sleepers
9,000m old rail
4,500m old conductor rail
and they installed:
5,650 sleepers
9,076m rail (113lb flat bottom)
1,482m check rail (used on small radius curves to prevent derailment)
4,450m third rail
2,870 insulator pots
685m3 concrete
900 signal relays
11 train stops
9 position detectors
23 point sets
11 signal post telephones
|