![]() |
| Return to Main Index | Names Encyclopedia | Internet Links | Dawlish Sea Wall |
| Notable Workings | Traction & Stock Recognition | Contributing illustrations | Contact Us |
| Network Rail set to re-open Rugby at 05.00 on 4 January
|
Network Rail has said that all the contractors involved in the Christmas-New Year engineering blockade at Rugby which has overun by four days will be the sbject of a major review. Network Rail confirmed during the afternoon on Thursday 3 January that the work at Rugby would be completed and the West Coast route reopen for services first thing on Friday morning. Iain Coucher, Chief Executive, said: "I can confirm that trains will start to run normally on the West Coast again from tomorrow. I can take no comfort from this news in the knowledge of the pain and inconvenience we have caused passengers over the past few days. I know that we have let passengers down with the over-run at Rugby. "An investigation into the causes of the over-run has been launched and I will be chairing a high-level meeting next week to review what's happened. I will be summoning our project managers, Bechtel, and the principal contractors involved to attend so they can personally explain to me what has gone wrong. They gave me assurances before Christmas on which they have not delivered. I want answers from them. The railway will be back tomorrow but the work is far from done. We have a significant programme for developing and expanding the railway over the coming years and we have to make certain that it is carried out to plan." • The work at Rugby over the Christmas break was a vital component to the overall scheme introducing new tracks, and enabling the next stages of work to commence as planned. • The work at Rugby over Christmas included:
On the route from London Liverpool Street the route was finally returned to a six track railway from around 10.00 on Thursday 3 January, allowing a near normal service to resume. |
| Last Updated: 3 January 2008 |
| © The RailwayCentre.Com Ltd 2006-2008 |