Network Rail is to investigate the options for improving train services
on the Cotswold Line between Oxford and Worcester. This announcement
follows a series of meetings with stakeholders and regional MPs this
week.
A feasibility study will examine options for improving train performance
and allowing an hourly service along the route. Large sections of
track were singled in the 1970's and today only 10 miles of double
track remain on the 51 mile route.
The feasibility study will examine:
* Possibilities of redoubling some or all of the three single line
sections of track between Oxford and Worcester
* Line speed improvements to reduce journey times and allow a more
flexible timetable for passengers
* Implications for stations - for example requirements for new platforms,
footbridges and DDA compliance
* Signalling improvements necessary to support the redoubling options
* The capability of the route to handle rail freight
Robbie Burns, Network Rail's Route Director said: "Network Rail
is committed to growing the railway in Britain, and we are well aware
of the aspirations of passengers and stakeholders along the Cotswold
Route. This study is important and will provide us with the necessary
detail to make informed decisions on what options are possible, and
affordable."
The £150k cost of the study will be funded by Network Rail and
is expected to report in Autumn 2007.Any final decision on what improvements
will be implemented will be based on the cost, deliverability and
value for money of each option. Implementation of the recommendations
would be delivered by 2010, subject to securing the necessary funding.
The study will examine the 51 miles route between Wolvercot Junction
(west of Oxford) via Moreton-in-Marsh and Evesham to Norton Junction
(east of Worcester). 80% of this route was singled in 1960s/70s.
The route comprises of 4 sections:
1 - Wolvercot Junction (Oxon) to Ascott under Wychwood: Single Track
(14 miles)
2 - Ascott-under-Wychwood to Moreton in Marsh: Double Track (11 miles)
3 - Moreton in Marsh to Evesham: Single Track (15 miles)
4 - Evesham - Norton Junction (Worcs) Single Track (11 miles)
|