|
A £55 million
investment programme that will completely renew the railway through
the centre of Lincoln, has been announced by Network Rail. Starting
next spring, the track and signalling through the centre of the city
will be renewed, the track layout will be improved, and a new state-of-the-art
signalling control centre will be built at West Holmes.
Network Rail Route Director Dyan Crowther said: This project
represents a major investment in the area, and will give Lincoln a
brand new railway fit for the 21st century. The new track and
signalling will benefit passengers with a more reliable service.
Improvements to the track layout and the removal of several speed
restrictions will speed trains up and reduce the amount of the time
the citys level crossing barriers need to be lowered.
Work on the project starts in April 2007. Several closures of
the railway through the city will be necessary in the summers of 2007
and 2008 to allow engineers to install the new track and signalling.
During these periods there will also be some short term level crossing
closures. Network Rail is working closely with train operators,
local authorities and other stakeholders to ensure the closures are
well planned, and that disruption is kept to an absolute minimum.
Dyan Crowther added: Weve listened carefully to people
in Lincoln and the train operators to ensure we are able to carry
out this important work with the minimum disruption to passengers,
motorists and pedestrians. For example a lot of the work will
take place over the summer during the school and University holidays
when there is less traffic on the roads.
The new track and signalling will be operational by September 2008,
and the project will be completed in early 2009.
Project Timescales; To minimise disruption, the project will take
place in two phases: Phase 1: Preparatory works start in April 2007
including establishing site offices and facilities. In July 2007 the
level crossing at Sincil Bank (Great Northern Terrace) will be closed
for periods over several weekends as new track is installed through
the crossing. August 2007 will see a 3 week closure of the railway
through Lincoln while new track equipment and cabling is installed.
The work will require some closures of Sincil Bank and Brayford level
crossings. Phase 2: In 2008 the railway through Lincoln will be closed
for 6 weeks between July and September, subject to agreement with
the Train Operating Companies. New signalling, level crossing equipment
and track will be installed and fully tested before the line reopens.
The work will also necessitate the closure of High Street Level Crossing
and other level crossings during some of this period
Network Rail will work closely with Central Trains and Northern Rail
to ensure passengers are informed of any timetable alterations. Network
Rail will also work closely with Lincolnshire County Council to ensure
any temporary diversionary routes for motorists and pedestrians are
well publicised and signposted in advance.
The project will renew signalling equipment, track and telecoms infrastructure
on the railway in the heart of Lincoln. High Street Level Crossing
will be fitted with CCTV control and this together with the other
existing CCTV level crossings will be re-controlled from the new Signalling
Control Centre at West Holmes. The 4 signal boxes at Pelham Street,
High Street, East Holmes and West Holmes will close as signalling
in the city will be controlled from the new Signal Control Centre.
The new railway will remove speed restrictions (specifically one at
Pelham which currently limits trains to 10mph) enabling trains to
move through Lincoln quicker, with reduced barrier time at level crossings.
Remodelled track and bi-directional signalling will reduce the amount
of shunting needed on the line. This will reduce the time needed for
trains to turn around improving performance for passengers.
Less shunting will also reduce the number of times the level crossing
barriers are down
|